Guide · Bluebeam Revu

How to do a concrete takeoff in Bluebeam Revu

A volume trade measured as areas and lengths. Read the dimensions off the notes and schedules, measure each element its own way, keep rebar, formwork and finishing separate, and add waste once at the end.

Last reviewed . Revu’s panels move between versions. If a step here no longer matches what is on your screen, tell us and we will fix it.

The short version

Read the structural notes and schedules first. Set and check the scale. Measure slabs as area with depth, continuous footings, walls and grade beams as length times section, and spread footings and piers as counts by type. Pick up thickenings, take out openings and overlaps, keep rebar, formwork and finishing as their own quantities, then add waste once and round each pour to what you can order.

The rest of the Revu workflow is in How to do a takeoff in Bluebeam Revu, and the setting every volume depends on is in How to set the scale in Bluebeam Revu.

Concrete takeoff, in order

01

Read the structural notes and schedules before the plan

The S-sheets carry most of what a concrete takeoff needs, and little of it is on the foundation plan itself. Slab thickness and base course are in the general notes or a typical section. Footing sizes are in the footing schedule. Pier diameters and heights are in a pier schedule or on a detail. Wall thickness changes are on sections that can be several sheets away.

Read those first, and write each element type down with the dimension that is not on the plan: "SOG, 5 in", "F1, 4 ft by 4 ft by 18 in", "GB-1, 18 in by 30 in". The plan gives you where and how much. The notes and schedules give you how thick or how deep, and a takeoff that guesses the second half is wrong in every row.

02

Set the scale, then build one tool per element type

Calibrate the page against a long, dimensioned string before you trace anything, and check it against a second one. Every area, length and volume on the sheet inherits the scale, so an error here is in every number at once.

Then build a Tool Chest of measurement tools named by element: an Area or Volume tool for each slab type, Polylength tools for each continuous footing, wall and grade beam type, and Count tools for each spread footing and pier type. Give each a subject and colour of its own. A Markups list where every line says "Area" is a list nobody can price from.

03

Measure slabs as areas with a depth

Revu’s Volume tool takes a traced shape and a depth and reports the volume in the units of the page scale, so a slab traced in feet with a depth in inches comes back in cubic feet. Cutouts work inside a volume the same way they do in an area. The other way is to trace an Area and carry the thickness in a Custom Column with a formula. Either is fine; pick one per job so the list reads the same top to bottom.

Elevated slabs on metal deck are not their nominal thickness all the way through. The concrete fills the deck flutes, and the deck manufacturer publishes a concrete volume for each deck profile and total slab depth. Use that figure, not the full thickness times the area.

As an example only: a 10,000 SF slab on grade at 5 in thick is 10,000 times 5 divided by 12, or about 4,167 CF, which is about 154 CY before waste. Keep that arithmetic visible in the list, because it is the line somebody will question on bid day.

04

Run continuous elements as length times section

Continuous footings, foundation walls, grade beams and curbs are long shapes with a constant section. Trace the centreline with Polylength, then multiply the length by the width and depth from the schedule or section. A Custom Column formula keeps that multiplication in the Markups list where it can be checked.

Corners are where these quantities go wrong. Two footings traced to their outside edges overlap at every corner, so trace centrelines, or trace outside on one leg and inside on the other, and do it the same way everywhere. Step footings and wall height changes are separate segments with their own section, not an average.

05

Count spread footings and piers by type, then multiply

Spread footings and piers repeat. Count each type from the schedule as its own count, F1, F2, F3 and each pier mark, then multiply the count by the volume of one. That is faster and easier to check than tracing each footing, and it ties every footing on the plan back to a row on the schedule.

A footing or pier mark on the plan with no schedule row is a stop, not a guess. So is a schedule row that never appears on the plan. Either one is a question worth an RFI before it is a number in the bid.

ElementMeasure asDimensions fromWatch for
Slab on gradeArea with depth (CF, then CY)General notes, typical slab sectionThickenings, depressions, base course
Elevated slabArea with deck volumeFraming plan, deck manufacturer volumeOpenings and shafts, deck profile
Continuous footingLength times width times depthFooting schedule, wall sectionsCorner overlaps, step footings
Spread footingCount by type times one volumeFooting scheduleMarks with no schedule row
Foundation wallLength times height times thicknessWall sections, elevationsHeight changes, pilasters
Grade beamLength times width times depthGrade beam schedule or sectionOverlap with piers and caps
PierCount by type times one volumePier schedule, detailsLength set in the field, bell bottoms
CurbLength times sectionSite detailsCurb and gutter as one section
06

Pick up thickenings and edges, and take out what is not concrete

Thickened slab edges, turndowns, interior thickenings under bearing walls and depressed slabs at showers or entries all add concrete the slab thickness does not cover. Measure them as their own lengths with their own sections, from the details, and keep them as separate lines rather than bumping the slab thickness to make up for them.

Then take out what is not concrete. Large openings, shafts and stairs in elevated slabs come out. Where a slab sits on top of a footing, count the overlap once, not in both elements. Decide your rule for small penetrations and blockouts at the start and use it the whole way through.

07

Keep rebar, formwork and finishing as their own quantities

One concrete element drives several prices. Formwork is measured as contact area, the square feet of form face that touches the concrete, so it comes from the edges and sides, not the plan area. Rebar is weight, from the bar schedule or the typical reinforcing details. Finishing is the plan area of the exposed surface, split by finish type. Slab edge form, vapor retarder, base course and joints each have their own unit.

Take them off from the same markups where you can, but keep them as separate named quantities. A cubic yard figure with formwork folded into it cannot be checked against a forming sub’s quote, and a forming quantity that was never measured is the one a sub-quote comparison catches too late.

08

Add waste once, at the end, then round to what you can order

Keep the measured net volume clean. Add your waste allowance once, at the end, per element type if your shop treats footings poured against earth differently from formed slabs, and show it as its own line. Waste added inside a trace and again on the total is waste counted twice.

Then convert to cubic yards, divide cubic feet by 27, and round each pour up to the increment your supplier sells in. Rounding happens per pour, not just on the grand total, because each truck order is its own order. Export the Markups list to CSV or Excel and the conversion, the waste and the rounding can all be checked in one place.

  • Guessing a thickness the notes give you

    Slab, footing and wall dimensions live on the notes, schedules and sections. A takeoff that assumes them is wrong in every row it touches.

  • Double-counting footing corners

    Two continuous footings traced to their outside edges overlap at every corner. Trace centrelines, and do it the same way everywhere.

  • Pricing a deck slab at full thickness

    Concrete on metal deck fills the flutes. The deck manufacturer’s volume table is the number to use.

  • Counting the slab over the footing twice

    Where the slab sits on a footing, the overlap belongs to one element. Decide which, and keep to it.

  • Missing thickened edges and turndowns

    They are on the details, not the plan, and they add real concrete along the whole perimeter.

  • Folding formwork and rebar into the yards

    Different units, different subs, different quotes. Keep them as their own quantities so each can be checked.

  • Adding waste twice

    Once inside the trace and again on the total is two allowances. Add it once, at the end, on its own line.

  • Rounding only the grand total

    Each pour is its own truck order. Round each one up to the supplier’s increment, not just the sum.

Questions people ask

Does the Revu Volume tool give cubic yards for a concrete slab?

It reports volume in the units of the page scale, so a slab on a sheet scaled in feet comes back in cubic feet, even when the depth is entered in inches. Divide by 27 for cubic yards, either by hand or with a Custom Column formula in the Markups list.

How do I take off continuous footings without counting the corners twice?

Trace the footing centreline with Polylength and multiply by the width and depth from the schedule. Centrelines meet at a point, so each corner is counted once. If you trace edges instead, trace outside on one leg and inside on the other, the same way every time.

Should spread footings be traced or counted?

Counted, by type. Count each footing mark from the schedule as its own count, then multiply by the volume of one footing of that type. It is faster than tracing, and every footing on the plan ends up tied to a row on the schedule.

How much concrete is in a slab on metal deck?

Less than the area times the total thickness, because the concrete fills the deck flutes rather than a solid block. The deck manufacturer publishes a concrete volume for each deck profile and slab depth. Use that figure with the measured area.

When do I round concrete up to the next order increment?

At the very end, after waste, and per pour rather than only on the grand total. Each pour is its own truck order, so the rounding happens where the order happens. Keep the net volume, the waste and the rounded order as three visible numbers.

The faster way through it

Or ask for the quantities out loud

“Area of the slab on grade on S-101, and count the F1 and F2 footings.” Our AI model reads the sheet, works out which elements the scope covers, and drives the Bluebeam Revu you already have open to measure them. They land in your Markups list as native, editable markups, named by element the way you asked for them. It asks before it writes.