Last reviewed . Section numbers and titles follow MasterFormat 2018. If your team reads Division 01 a way this guide misses, tell us and we will add it.
The short version
Read Division 01 next to Division 00, front to back, before you send a single scope letter. Mark the phasing and work hours, what every allowance covers, the unit prices and alternates, the meetings and schedule, the submittal rules, who pays for testing, every temporary facility, and the closeout and warranty terms. Then sort each one: general conditions, a sub’s scope, or a qualification.
Related: how to write a scope of work and how to catch scope gaps in sub quotes.
Division 01, section by section
Read 01 10 00 Summary for what the job actually is
Summary is short and it changes the whole estimate. 01 11 00 Summary of Work tells you about work by the owner and owner-furnished items you will install, which you have to receive, store and set without buying. 01 12 00 Multiple Contract Summary tells you if other prime contractors share the site. 01 14 00 Work Restrictions is where the occupied building, the restricted work hours, the phasing and the "owner will continue to operate" sentence live.
Each of those is time and money. A phased job in an occupied building means more mobilizations, temporary partitions, after-hours work and a longer general conditions duration. Carry the duration and the premium labor in your general conditions, and put the phasing and work hours in every sub’s scope so they price the same job you did.
Before you go further, check how this manual relates to Division 00. The contract General Conditions, often AIA A201, and the Supplementary Conditions sit in Division 00. Division 01 expands on them. Read the two together, because insurance, bonds and retainage are usually in 00, while the procedures that cost you money are in 01.
Work through 01 20 00 Price and Payment Procedures line by line
01 21 00 Allowances lists the money you carry for scope that is not designed yet: hardware, signage, a testing budget. Read exactly what each allowance covers. Under the AIA A201 general conditions, unless the documents say otherwise, an allowance covers the material delivered to site and the taxes, and your unloading, handling, installation, overhead and profit go in the contract sum outside it. So a material-only allowance still needs a labor line next to it in your bid.
01 22 00 Unit Prices lists the rates the owner wants for adding or deducting work, like rock excavation per CY or unsuitable soil per CY. Send each one to the sub who carries that work, ask for it on its own line, and check the rates against your own costs. 01 23 00 Alternates describes each alternate on the bid form. Read the description, not just the title, because it often changes more than one trade.
01 25 00 Substitution Procedures tells you whether substitutions are allowed during bidding and by what deadline. 01 29 00 Payment Procedures covers the schedule of values and pay applications. Neither costs much to price, but missing a prior-approval deadline means you bid the named product whether you like it or not.
Price the people time in 01 30 00 Administrative Requirements
01 31 00 Project Management and Coordination is where coordination drawings, BIM requirements, project meetings and the web-based project management software live. Weekly OAC meetings, a coordination process for MEP in the ceiling, and a named platform are all staff hours. They go in your general conditions as PM, superintendent and project engineer time.
01 32 00 Construction Progress Documentation sets the schedule requirements, from a bar chart to a resource-loaded CPM with monthly updates, plus progress photos and sometimes a site camera. A scheduling consultant or a camera service is a line item. 01 35 00 Special Procedures covers things like alteration work in existing buildings, infection control in healthcare, and security clearances for workers, and each of those can add to every trade on site.
Check 01 33 00 Submittal Procedures for format and turnaround
Submittal Procedures tells you how submittals move: the electronic platform, the review time the architect gets, how many resubmittals are reviewed before the owner charges for more, and what each submittal has to contain. A long review time with a tight schedule means you start submittals the day you are awarded, and someone on your staff has to run them.
Look for the clause that charges the contractor for the architect’s time on extra resubmittals, and the one that requires delegated-design submittals stamped by an engineer. Delegated design, common for cold-formed framing, stairs and fire protection, has to be in the sub’s scope by name, or you pay for the engineer.
Find out who pays for testing in 01 40 00 Quality Requirements
01 41 00 Regulatory Requirements points at the codes and the permits. Check who pulls and pays for the building permit and the trade permits. 01 43 00 Quality Assurance often holds the mockups, under 01 43 39 Mockups. A full exterior wall mockup is real work: framing, sheathing, a window, cladding, sealants, often a water test, and then demolition. Price it as its own line or make sure each trade carries its piece.
01 45 00 Quality Control, with 01 45 23 Testing and Inspecting Services, says who hires the testing agency. The usual pattern is that the owner pays for the testing and the contractor pays for retests after a failure, but read your section, because some jobs put the whole testing budget on the contractor or carry it as an allowance in 01 21 00.
Price the jobsite from 01 50 00 Temporary Facilities and Controls
This section is your general conditions in spec form. 01 51 00 Temporary Utilities says who provides temporary power, water, heat and lighting, and who pays for what they consume. 01 52 00 Construction Facilities covers field offices, an owner’s field office if one is required, and toilets. 01 54 00 Construction Aids covers hoisting and scaffolding.
01 56 00 Temporary Barriers and Enclosures covers fencing, dust partitions in occupied buildings, and weather enclosures for winter work. 01 57 00 Temporary Controls covers erosion and sediment control and dust control, and 01 58 00 Project Identification covers the project sign. Decide line by line whether each item is a GC cost or belongs in a sub’s scope. Temporary heat, for example, is often carried by the GC, with the mechanical sub running the permanent system early under a written agreement.
Price the finish line from 01 70 00 Execution and Closeout Requirements
01 71 00 Examination and Preparation holds field engineering and layout, which you either self-perform or hire a surveyor for. 01 73 00 Execution often holds 01 73 29 Cutting and Patching, which decides who patches when one trade cuts another’s work. Put that answer in every sub’s scope. 01 74 00 Cleaning and Waste Management sets the cleaning standard, final cleaning, and, under 01 74 19, the waste diversion target and the paperwork to prove it.
01 77 00 Closeout Procedures and 01 78 00 Closeout Submittals are where the back end costs live: O&M manuals under 01 78 23, warranties under 01 78 36, and record documents, the as-builts, under 01 78 39. Check for warranty terms longer than one year and make sure the sub who installs that work carries them. 01 79 00 Demonstration and Training sets owner training hours, and 01 91 00 Commissioning, in the 01 90 00 group, can add a commissioning agent’s meetings and functional tests to the mechanical and electrical subs.
Sort every finding into general conditions, a sub’s scope, or a qualification
Everything you marked in Division 01 ends up in one of three places. If the GC does it or pays for it, it goes in your general conditions. If a trade does it, it goes in that trade’s scope letter with the section number, so the sub prices it and you can check that they did. If it is unclear, unreasonable, or depends on something the owner has not decided, it goes in your proposal as a qualification or out as a question during bidding.
The table below is a starting map. Your manual will move things around, so use it as a list of places to look, not a list of answers.
| Section | What hides there | Where it usually goes in the bid |
|---|---|---|
| 01 11 00 Summary of Work | Owner-furnished items you install, work by owner | Sub scope for install; GC for receiving and storage |
| 01 14 00 Work Restrictions | Occupied building, work hours, phasing | General conditions duration; every sub’s scope |
| 01 21 00 Allowances | What each allowance does and does not cover | Bid form as listed; labor and markup outside it |
| 01 22 00 Unit Prices | Add and deduct rates the owner will hold you to | Sub scope, priced on its own line |
| 01 23 00 Alternates | Alternates that touch more than one trade | Each affected sub, priced separately |
| 01 25 00 Substitution Procedures | Prior-approval deadline during bidding | Bid schedule; a question if the deadline is missed |
| 01 31 00 Project Management and Coordination | Meetings, coordination drawings, BIM, software | General conditions staff time; MEP sub scopes for coordination |
| 01 32 00 Construction Progress Documentation | CPM schedule, updates, photos, site camera | General conditions |
| 01 33 00 Submittal Procedures | Review time, resubmittal charges, delegated design | General conditions; delegated design in the sub’s scope |
| 01 43 39 Mockups | Full assemblies built, tested and removed | Each trade’s scope, or its own line |
| 01 45 23 Testing and Inspecting Services | Who hires the agency, who pays retests | General conditions for retests; a qualification if unclear |
| 01 50 00 Temporary Facilities and Controls | Power, water, heat, toilets, hoisting, fencing, enclosures | General conditions, item by item; some to subs |
| 01 73 29 Cutting and Patching | Who patches after another trade cuts | Every sub’s scope |
| 01 74 19 Construction Waste Management and Disposal | Diversion target and reporting | General conditions for dumpsters; subs for sorting |
| 01 78 36 Warranties | Terms longer than one year, special warranties | Sub scope; a qualification if a term is unusual |
| 01 78 39 Project Record Documents | As-built requirements, format, who draws them | Sub scope for their trade; GC for the set |
| 01 91 00 Commissioning | Agent meetings, functional tests, retests | MEP sub scopes; general conditions for GC time |
Skipping Division 01 because "it is the same on every job"
The headings are the same. What is under them changes: the review time, the testing split, the warranty term, the work hours. Read it on every job.
Pricing an allowance as an installed number
If the allowance covers material only, the labor to install it is yours to carry. Read what the allowance covers before you put it on the bid form.
Leaving Division 01 out of the scope letters
If a sub’s scope does not name the cleanup, the hoisting, the mockup and the warranty, the sub did not price them, and the GC will.
Missing the substitution deadline
Prior approval during bidding usually has a cutoff before bid day. Miss it and you bid the named product.
Reading Division 01 without Division 00
Retainage, insurance, bonds and liquidated damages usually sit in the Supplementary Conditions. Division 01 makes sense only next to them.
Assuming testing is the owner’s
It often is, apart from retests. Sometimes it is not. One sentence in 01 45 00 decides it.
Questions people ask
What is Division 01 in a construction spec?
Division 01 General Requirements is the part of the project manual that applies to the whole job rather than to one trade. In MasterFormat it covers the summary of work, price and payment procedures, administrative requirements, quality, temporary facilities, product requirements, and execution and closeout. Every technical section in Divisions 02 onward assumes it.
What is the difference between Division 00 and Division 01?
Division 00 holds the procurement and contracting documents: the bid instructions, the bid form, the agreement, the General Conditions and the Supplementary Conditions. Division 01 holds the general requirements that put those terms into practice on site, like submittal procedures, temporary facilities and closeout. Read the two together.
Does an allowance include labor and markup?
Under the AIA A201 general conditions, unless the documents say otherwise, an allowance covers the material delivered to site and the taxes on it, and the contractor’s handling, installation, overhead and profit go in the contract sum outside the allowance. Your project may say something different in 01 21 00, so read the section.
Where do Division 01 costs go in a bid?
In one of three places. GC work and costs go in your general conditions. Work a trade performs goes in that trade’s scope, with the section number, so the sub prices it. Anything unclear or not yet decided by the owner goes in a question during bidding or a qualification in your proposal.
What if my project manual numbers Division 01 differently?
Many do. Older manuals use the five-digit numbers from before 2004, and specifiers often combine or rename sections. Use the table of contents and search the manual for the topics, like allowances, mockups and warranties, rather than relying on the section number.
Caliente Vision
Caliente Vision reads Division 01 against every package
Caliente Vision reads Division 00, Division 01, the trade sections and the addenda your team already has, and lists each general requirement that adds cost, with the section it came from. It connects each one to the general conditions or the scope letter that should carry it, and flags the ones nothing carries yet. It drafts the scope language and the questions; your estimator approves them before anything is sent. Caliente Vision finds, connects and checks. Estimators decide.
Why we built it: Introducing Caliente Vision.